The Corporation of the Township of Laird
Roads Department 5-Year Plan 2025 to 2029
Township of Laird – 5-Year Road Plan, 2025 to 2029
Approved by Motion #: 06-25, January 16, 2025
2025 Draft
Double Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| NOTE: Remove from plan |
Single Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| Bar River Road Tracks to Cemetery Road | 3600 meters | |
| NOTE: Remove from plan | ||
| Government Rd – Riley Road to Bar River Road | 3600 meters | NOTE: New to plan |
| Calabogie – Lakeview to Lakeshore | 1000 meters | NOTE: New to plan |
| Neebish – Highway to MacDonald Drive | 1600 meters | NOTE: New to plan |
Resurface Gravel
| Road | Activity | Rational |
|---|---|---|
| NOTE: Remove from plan | ||
| NOTE: Remove from plan | ||
| NOTE: Remove from plan | ||
| Yard (stock) | 20 loads | |
| Lake George Road | 40 loads (capital) | NOTE: New to plan |
Ditching
| Road | Activity | Rational |
|---|---|---|
| Rydall Mill Road | from #87 east to #178 north side 450 meters | |
| Finns’ Bay Road | Neebish west 300 meters to # 73 north side |
Culverts
None listed.
Estimated costs:
- Road repair in preparation for surface treatment will be approximately $14,600.00 (capital)
- Surface treatment to cost approximately $265,320.00
- Gravel costs approximately $30,000.00
- Rental of brushing equipment to conduct heavy brushing of all of Township – Approximately $10,000.00
2026 Draft
Double Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| Lake George Road | Double 1,650 meters | NOTE: New to plan |
Single Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| Government Road | Townline to | |
| Same road as above | Townline Highway to Government | 1,600 meters |
| Same road as above | Lapish Road | 1,400 meters |
Resurface Gravel
| Road | Activity | Rational |
|---|---|---|
| Yard (stock) | 25 loads | |
| Lake George Road | 40 loads (capital) | NOTE: New to plan |
Ditching
| Road | Activity | Rational |
|---|---|---|
| Neebish Road West | MacDonald Drive to Finns’ Bay Rd | 800 meters north side |
Culverts
None listed.
Estimated costs:
- Road repair in preparation for surface treatment will be approximately $10,500.00
- Surface treatment to cost approximately $318,500.00
- Gravel cost approximately $35,750.00
2027 Draft
Double Surface Treatment
None listed.
Single Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| Government Road | Pumpkin Point to | |
| NOTE: Removed from plan | ||
| Pumpkin Point Rd East | Government to Highway | 1600 meters NOTE: New to plan |
Resurface Gravel
| Road | Activity | Rational |
|---|---|---|
| Yard (stock) | 20 loads | |
| Riverside Drive | 30 loads | NOTE: New to plan |
| Cemetery Road | 20 loads | NOTE: New to plan |
Ditching
| Road | Activity | Rational |
|---|---|---|
| Lake George Road West | 1050 meters bridge east to #104 south side | |
| Pumpkin Point Road West | 150 meters Lakeview west to cross culvert south side |
Culverts
None listed.
2028 Draft
Double Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| Riverside Drive | 1,000 meters new surface treatment | NOTE: New to Plan |
Single Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| Neebish Road West |
Resurface Gravel
| Road | Activity | Rational |
|---|---|---|
| Yard Stock | 20 loads | |
| Riverside Drive | 30 loads | NOTE: New to Plan |
| Cemetery Road | 30 loads | NOTE: New to Plan |
Ditching
| Road | Activity | Rational |
|---|---|---|
| Calabogie – South Side | Rydall’s to Lake, approximately 1,000 meters | |
| Lake George Road East | Bottom of hill to large Cross Culvert, approximately 700 m |
Culverts
| Road | Activity | Rational |
|---|---|---|
| Large cross culvert on Lake George Road | 60 feet x 8 feet |
2029 Draft
NOTE: 2029 is new to plan
Double Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| Cemetery Road | 1,000 metres |
Single Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| Pumpkin Point Road West | Highway to Porchuck 3,200 metres |
Resurface Gravel
| Road | Activity | Rational |
|---|---|---|
| Cemetery Road | 30 loads | |
| Lake Shore Drive | 20 loads | |
| Yard | 20 loads | |
| Hillstrom Road | 10 loads |
Ditching
| Road | Activity | Rational |
|---|---|---|
| Lakeshore Drive | All West and East sides 1,400 meters | |
| Hillstrom Road | West side 500 meters |
Culverts
None listed.
2030 Draft
NOTE: 2030 is new to plan
Double Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| Lake Shore Drive | 700 metres | |
| Hillstrom Drive | 500 metres |
Single Surface Treatment
| Road | Activity | Rational |
|---|---|---|
| Townline Road West | 1,400 metres |
Resurface Gravel
| Road | Activity | Rational |
|---|---|---|
| Yard | 20 loads | |
| Hillstrom Road | 10 loads |
Ditching
| Road | Activity | Rational |
|---|---|---|
| Reids Road | Both sides | |
| Highway to Lakeview | 3,200 metres |
Culverts
None listed.